In 1979, the company setup its first Rolling mill and followed it up with a massive programme of verticals and horizontal integration, there by commissioning: Wire Rod Rolling Mill (1982-83), Induction furnaces (1985-86), Oxygen Plant (1989), Steel Wire Drawing Unit (1991), Tyre Bead Wire Unit (1993), Electric Arc Furnace(1995).
|
Facilities |
Plant Capacity |
Engineering/Make |
ELECTRIC ARC FURNANCE (EBT/UHP) with facility for eccentric bottom tapping and continuous feeding system for D.R.I./H.B.I/SPONGE Iron -Ensures slag free tapping |
30 MT |
ABB |
|
LADDLE FURNACE used for secondary refining of steel, - Corbon injection Machine Helps making slag foamy. - Dual wire feeding arrangements exits for (AL.CA-SI) |
EQUAL CAPACITY |
21st CENTURY |
|
LADDLE DEGASSING (STEAM EJECTOR VACUUM PUMP SYSTEM - 5 STAGES) |
35MT |
VOIEST ALPINE |
|
CON-CAST MACHINE |
6/11 METER 3 STRANDS |
CONCAST ZURICH |
|
ELECTRO MAGNETIC STIRRER |
|
AEG ELOTHERM COMBI - TYRE |
|
3 ROLLING MIILS ( 5 STRANDS 3 HIGH) |
18",12" & 10" |
|
|
ROUGHING STAND |
28" |
|
|